wedofloor-25Stipulated paint system
Product Details
Product features
Paint 1 - The paint dries in half an hour and requires two coats of rolling application. After drying, a gloss coating is needed to achieve excellent wear resistance, with a gloss ranging from 40 to 70.
Paint 2 - Epoxy marking paint, it dries in 4 hours, requires two coats of rolling application, has excellent adhesion, and has a gloss of approximately 80 to 90.
Paint 3 - Acrylic polyurethane, it dries in 15 minutes, requires one coat of rolling application, has a fast drying speed, and has a gloss of 65 to 75.
Scope of application
Paint 1 - Mainly used for marking on epoxy, polyurethane and other organic floors. Not suitable for use on smooth, wear-resistant and cured floors;
Paint 2 - Can be used for marking on various floors. It is the preferred material for marking on inorganic concrete floors (wear-resistant, cured, etc.);
Paint 3 - Mainly used for marking on epoxy, polyurethane and other organic floors. It is not prone to edge roughness on textured orange peel or other sandblasted floors.
| Coating | Material Model | Packaging Specification | Mixing Ratio | Material Usage (kg/m²) | Construction Thickness (mm) |
| Line Marking Paint 1 | OVG-0101/OVG-0102 Polyurethane Epoxy Floor Paint | 15KG/20KG | 0 | 0.3 (2 coats of color + 1 coat of clear) | 0.20 |
| Line Marking Paint 2 | WEDO-2203 High-solid Universal High-gloss Topcoat | 20KG/5KG | 0 | 0.2 (2 roller coats) | 0.16 |
| Line Marking Paint 3 | WEDO-H2203 Acrylic Polyurethane Fast-drying Line Marking Paint | 20KG/5KG | 0 | 0.25 (1 roller coat) | 0.20 |
Notes
Choose the appropriate marking paint as needed to avoid rework due to improper selection of the marking paint;
After the surface layer is completed, marking should be done promptly to avoid surface contamination causing problems such as poor adhesion of the marking paint;
During marking, the masking tape must be adhered firmly and must not be loose or have any gaps;
When using all marking paints, the materials must be mixed strictly according to the ratio; inaccurate ratio will cause the lines to dry incompletely, be sticky and difficult to clean, and even result in yellowing of the lines;
When marking on inorganic floors such as wear-resistant, curing, and self-flowing cement floors, only marking paint 2 can be selected;
When marking on orange peel textured or sandblasted floors, only marking paint 3 can be selected;
Technical Statement
Our company can design construction plans of different specifications (thickness, effect, etc.) through flexible matching and combination of various products to meet the personalized requirements of all kinds of customers. To ensure that your project can select the appropriate floor system, please consult our professional technical advisors. However, when using our company's products, please strictly follow the construction process, dosage requirements and precautions of the product. Otherwise, our company will not bear any responsibility for the quality of the project or any losses.
| Construction Process | Detailed Practices and Requirements | Single-pass Usage (kg/m²) |
| Substrate Treatment | 1. Ensure the topcoat is completely dry. | / |
| 2. Ensure the ground is free of contamination and kept clean. | ||
| Pattern Line Marking & Masking Tape Application | 1. Mark the layout lines with a color pen according to the shape on the drawing, and repeatedly check to ensure no deviation. | / |
| 2. Pay attention to the reference points during layout to ensure accuracy, and mark the layout lines with a color pen at the same time. | ||
| 3. Apply the masking tape firmly along the graphic to prevent edge lifting. | ||
| Line Marking Paint Application | 1. Confirm the required colors for each area and construct as specified. | 0.16 / 0.2 |
| 2. Select the appropriate line marking paint as needed and apply evenly without missing any areas. | ||
| 3. The masking tape can be removed after the topcoat surface is dry to prevent paint from seeping under the edges. |

Construction conditions
Air temperature: 5℃ – 30℃
Relative humidity: ≤ 80%
The construction site should have good ventilation;
Dew point temperature: The substrate and the uncured coating substrate must be 3℃ or more higher than the dew point temperature to reduce the risk of condensation or frosting on the floor coating.
Dirty floors need to be thoroughly cleaned; otherwise, it may affect the even application of the coating.
Indonesian
Malay
Vietnamese
Slovenian
Slovak
Latvian
Bosnian
Icelandic
Ukrainian
Georgian
Serbian
Croatian
Belarusian
Romanian
Estonian
Hungarian
Czech
Catalan
Norwegian
Lithuanian
Albanian
Hindi
Italian
Finnish
Arabic
Danish
Bulgarian
Thai
Polish
Swedish
Greek
Portuguese
Dutch
Turkish
Russian
Deutsch
French
Korean
Japanese
English